|

A western
Washington firms invention makes the grade.
By Janis
Keating
For most general
contractors, sidewalk preparation and grading can be a nuisance.
With their large earthmoving machines, sidewalk grading is
finer work than they can do efficiently, and the
concrete contractor never seems happy with the resultant grade.
In many cases, the concrete contractor has to dig out high
spots and fill in low spots, and often finds himself pouring
more concrete than is necessary, to compensate for the uneven
grade.
 |
PHOTO: TOPCON |
This problem is
virtually solved by Eatonville, WAbased Sidewalk Grading
Systems SGS 2000 (www.sgs-2000.com),
a revolutionary attachment to compact excavators that provides
a precise grade on which to set concrete forms. Using an SGS
2000, the job can be accomplished at a lower price than with
traditional methods, and often in half the time.
During 2004, in
Thurston County, WA, general contractor Tucci and Sons developed
Jubilee, a 134-lot residential area, which included
a professional golf course. Sidewalk Grading Systems (SGS)
was hired to prepare grade for 12,000 lineal feet of double-ribbon
sidewalk and 130 driveways. SGS completed the project in 10
days at a lower per-unit cost than with traditional grading
methods.
The soil
bed was sandy gravel, recalls Torrey Johnson, Jubilees
project manager. I believe our project was the first
time SGS had done a vertical curb, instead of a rolled curb
and gutter.
There was
also a planter strip inside the curb and gutter. In 10 days
we were finishedthe grading, the forming, and the concrete
pourat a significantly lower cost than what we could
have done ourselves. I think there was a 57-square-yard difference
between their cost and ours. The SGS 2000 worked pretty good,
although during the project [SGS] realized their current model
needed to be a bigger machine, with a bigger arm. Their next
prototype included that, and a GPS setup, for even more accuracy.
Depending upon their availability, we might use them again,
as our jobs often have tight, high-impact schedules.
Earlier this year,
SGS served Tucci and Sons once again, for a 40,000-foot job
of 5-foot sidewalks. The Washington State Department of Transportation
project, on SR 167, one of the states most congested
roadways, was a time-critical job; SGS worked at night when
two of the roads four lanes were closed to traffic.
SGS seemed
to work fairly well, Mike Cooper, Tuccis head
estimator, reports. They made modifications on the job
from what they originally started doingduring the project,
they had to fix the slope of debris, make it according to
specs. Right now I couldnt evaluate how much money they
saved usbut I know using SGS freed up a lot of our people,
without costing money, to get sidewalks done. SGS did it,
smooth and fast, for about the same money as wed bid.
We believed
there had to be a better way to grade sidewalk areas,
says SGSs General Manager Bill Culliton. Traditional
methods used very large machines, such as dozers, to
try to make the grade close. Due to the machines
size, you couldnt work parallel to the sidewalk; you
had to work perpendicular to it, which doesnt allow
you to get a very fine grade. The solution has always been
to grade low, and then the general contractor would put in
sand or crushed gravel to make the sidewalk bed levela
task accomplished with rakes, shovels, and hand compacterslots
of additional labor.
We come through
after you have the area two- or three-tenths within grade.
Our machine rides on the curb as a reference point, and the
grading blade is operated by the Topcon (www.topcon.com)
leveling system. As we drive along the curb and level, the
concrete crews can work behind us, putting in formswere
an extra step that saves money and time, Culliton says.
The SGS 2000, which
has evolved through four prototypes, now only fits the Komatsu
PC50, but weve also attached it to a Cat, and
were exploring the possibility of adapting it to John
Deere and Bobcat models. Minor modifications must be made
to the machines so we can attach our blade, and we need to
get manufacturers to approve our attachment, he explains.
The blade and its process is our invention; we adapt
it to excavators, and are looking to do so, to sell the finished
equipment outside the western Washington area.
The machines
operation isnt its only advantage; the blade can be
attached/detached in less than 30 minutes, whether one is
packing up to go home or changing the angle to work another
area. Mobility is a real plus for our method,
Culliton adds. A 2-ton pickup with a trailer can move
itthe excavator, blade, and roller.
Ceccanti Constructions
Bonney Lake project included 5,200 lineal feet of 5-foot-wide
sidewalk, and when SGS arrived on the scene, no asphalt was
yet on the roadway. The SGS 2000 made one pass in the native
windrow provided by the contractor, and then two more passes
in the five-eighths rock for the final gradeall within
three days.
SGS gave
me a 30% to 40% savings over what it wouldve cost me
and my guys with a backhoe, states Don Hanks, Ceccantis
superintendent. Plus, they did it in about half the
time it would have taken me. Their grade was right onthe
machine worked really good. Id have a hard time not
using them when I do another sidewalk.
In Tacoma, WA,
Woodworth Construction had a small job, 2,600
feet of 5-foot sidewalk, on which the company tried the SGS
process, because it was short on crews and needed to get the
job done. The project worked out very good; the SGS
folks were very professional, and they turned out a good product,
saving us about 30% in costs, says Project Manager Mark
Ballman. With the machine theyve developed for
this application, theyre more efficient than any other
way Ive seen before. Thats a good machine they
have there; they could corner the market with it.
A fifth prototype
of the machine is now underway. Weve modified
it for manufacturing purposes, Culliton explains. Weve
refined the process, made it more simple for a manufacturer
to build the machines for us. Were in the process of
making four units to sell to others; we own and operate two.
The SGS 2000 will carry a list price of about $89,000, which
includes the excavatorbut right now were making
$300 an hour by using our machines on projects, so it wont
take buyers very long to see the machine pay for itself. There
arent too many areas of the land development industry
in which youre rewarded for saving moneyyet, even
doing so, here we are, making profit for our customers, because
we can help them finish the job in less time, for less money.
Culliton estimates that bid pricing for finish costs is in
the neighborhood of $0.25 per square foot, $1.25 per lineal
foot, and $2.25 per cubic yard.
Another thing discovered
during the prototyping phase: Before a sidewalk gets
signed off by authorities, the process has left a 4- to 6-inch
drop in the lot. Contractors or the landscaper have to backfill
against that, taper it to ground next to it. Our equipment
can also be used to taper the grade, to backfilla process
that used to be done by hand. We can use the blade and bucket
of the machine to do this. Fill up the blade, grade the dirtalmost
like frosting a cake.
Janis Keating
is a frequent contributor to Forester Communications publications.
GEC
- November/December 2005
|