|
Technical lessons
learned in material handling at a demonstration site
By Robert Traver,
Andrea Welker, Clay Emerson,
Michael Kwiatkowski, Tyler Ladd, and Leo Kob

This article explores the
lessons learned from the construction of the porous concrete surface
for the Villanova University Porous Concrete Infiltration Best
Management Practice. At the time of construction, this site was
the first in the region to use porous concrete. Considerable knowledge
was gained in the construction and reconstruction of the surface.
The initial installation occurred in August 2002 and, because
of the failure of the original surface, was resurfaced in May
2003. The initial failure was caused by a number of elements,
the most significant being not understanding the impact the porous
concrete material properties had on construction practice. The
site was redesigned, and the resurfacing was performed, incorporating
the lessons learned during the initial failure. The second attempt
has been successful to date.
Project Overview
A porous concrete infiltration
BMP was constructed during the retrofit of an existing paved area
in the center of the Villanova University campus in Villanova,
PA, near Philadelphia. The contributing watershed is approximately
50,000 ft2 and highly impervious, consisting of pedestrian walkways,
rooftops, and some grass areas. The rooftops and some adjacent
paved areas are directly connected to three separate rock storage
beds (4 ft deep) that underlie the porous concrete surface. The
rock beds are linked through piping systems to distribute the
runoff between beds and allow for overflow during major storm
events. The original porous concrete surface was edged using decorative
pavers. Installation involved demolishing the original site, extensive
regrading, and construction of the infiltration BMP. The site
was designed to capture and infiltrate the first 2 inches of runoff,
thereby reducing downstream stormwater volumes, streambank erosion,
and nonpoint source pollution. The project joins the Villanova
University Best Management Practice Research and Demonstration
Park as both a research and a demonstration site (Traver 2002).
Funding for the project was provided through the Pennsylvania
Section
319 Nonpoint Source Pollution Program, and the site has been designated
as a national monitoring site by EPA. Further information on this
and other projects can be found by accessing the Villanova Urban
Stormwater Partnership (VUSP) Web site (www.villanova.edu/VUSP).
Initial Pour Observations
 |
| Figure
1. Infiltration BMP: initial surface |
The original design consisted
of three large porous surfaces bordered with pavers, as shown in
Figure 1. The original plan was for the material to be batched off-site,
poured and spread, leveled using a traveling vibratory screed, hand
compacted, and finally covered. An admixture to improve bonding
and thus strength of the concrete would be added to the drum at
the site prior to pouring. Before construction, a small test pad
(130 ft2) was poured, and a visual inspection proved it to be satisfactory
in porosity and strength. The chief concern from the test pad experience
was the cosmetic appearance of the material. Two tamping methods
(hand and vibratory) were tried.
The weather during pouring
was hot (95-100°F). The concrete was provided by a concrete plant
approximately 45 minutes away from the construction site; however,
this travel time was unpredictable because of traffic congestion.
When the truck arrived at the site, the admixture was added, mixed
thoroughly for approximately 15-20 minutes, and poured.
 |
| Figure
2. Iinitial pour and hand tamping |
 |
| Figure
3. Vibratory tamping |
The first truckload of
concrete lacked the desired consistency. The concrete resembled
wet, loose gravel and was discarded. It was assumed that too much
water had been added and that this prevented the concrete from curing
properly. The second truckload of concrete arrived shortly thereafter
and appeared to have a better consistency. It was poured and then
spread by shovels and rakes. The vibratory screed was not useful
because of the poor workability of the material (stiffness). After
the concrete was spread, a vibratory tamper was used to smooth and
lightly compact it. Originally a hand tamper was used (Figure 2).
Unfortunately hand tamping proved to be time-consuming, and the
laborers could not keep up with the pour. Later a vibrating push
tamper was modified with a larger bottom plate and used to finish
the concrete behind the screed (Figure 3). This technique was successful
because the compaction was distributed over a larger area, thereby
improving the final surface appearance.
There was a small window
of opportunity in which the concrete maintained its workability.
The third truckload became unworkable before it was poured completely.
The contractors and the admixture industry representative discussed
the issue and decided to dispose of the remaining material. By
this time, the fourth truckload already had arrived on-site and
had been sitting for a while. The material had already lost its
workability when it was time for it to be poured and thus could
not be used.
At the end of each day,
the porous concrete was covered with plastic sheets, but these
sheets were extremely difficult to hold in place because of the
size of the pour and gusting winds. They blew off long before
the recommended 48-hour cure time.
Similar events unfolded
in the following days. To better control and predict the workability
of the concrete, it was decided that the trucks should bring the
concrete mix to the site without the addition of any water. The
water would be added on-site, eliminating some of the uncertainties
in travel and mixing times. Occasionally the mix consistency would
be acceptable for placement, but the material often would become
unworkable. Portions of the material that did appear acceptable
at the time of placement did not cure properly. These portions
were removed and replaced the following day. After consultation
with the concrete plant, it was discovered that a retardant had
been added by the plant to delay setup because of the excessive
heat and dry conditions. This retardant was not documented on
the delivery sheets.
 |
| Figure
4. Color variations from patching |
Once the entire site
was constructed, it was clear that the final finish of the porous
concrete would not be acceptable. In many locations, the surface
of the concrete was rutted, while other areas did not set up at
all and resembled loose gravel. It was theorized that there might
have been cement in the concrete that had not yet hydrated. The
contractor brushed and wet the concrete in an attempt to promote
hydration. Many of the areas of loose gravel were removed and patched
with another batch of porous concrete. This created a tremendous
variation in color and texture of the concrete, as shown in Figure
4. Due to the start of classes, there was no time left for further
repairs.
Speculations
 |
| Figure
5. Ineffective covering |
Construction was restricted
to the summer months when the dormitories adjacent to the site were
vacant. Pouring began on July 30, 2002, and was completed on August
20. The pour occurred amid a severe heat wave with temperatures
consistently in the upper 90s to low 100s. This environmental factor
made the installation of the porous concrete difficult. Unpredictability
in the on-site mixing process caused curing to occur much too quickly.
The freshly poured concrete was covered with plastic sheets but
the ill-secured covers blew off soon after being laid down (Figure
5). The large size of the pour made covering difficult. Therefore,
the poured concrete was not allowed to properly hydrate, contributing
to the observed surface failure.
There were many inconsistencies
between the different loads, including travel and mix times. Some
of the loads had the concrete sitting for more than two hours
before the pour began. To eliminate the influence of variable
travel times on the concrete reaction time, it was decided that
water should be added on-site (after the first day). This also
allowed the workers to have better control of the amount of water
added per truck. Because of the extreme heat and often long travel
times, the plant had added a retardant to some of the trucks to
slow the reaction in the mix, a standard practice with conventional
concrete. The workers at the site were not made aware of the retardant,
however, and its effect on porous concrete containing a bonding
agent were not known. It also was found (after construction was
completed) that the aggregate used was not washed as specified
and contained excessive fines. These fines absorbed water, thereby
increasing the amount of water required. Because the composition
of each load varied (i.e., additives, fine content), it was impossible
to determine the proper volume of water to add. The inability
to accurately know and control the mix contributed to the surface
failure.
The traveling vibratory
screed used to level and compact the concrete proved cumbersome
and ineffective. The screed was used because the pours were 15-25
ft wide. Simply moving the concrete material side to side was
difficult. The setup speed was fast compared to conventional concrete,
and the end of a full drum's pour often was difficult to work,
leading to ruts and irregularities in the surface appearance.
Covering the concrete to
promote hydration was ineffective. After the concrete had been
poured and compacted, it was sprayed with the additive and water
mixture, as per the specifications, and then covered with large
sheets of plastic. The plastic was not put down until 15-20 minutes
after compaction (or later). During the heat of the day, this
delay in covering the fresh material might have played a significant
role in the failure of the surface. Although this was apparently
a normal construction practice for regular concrete, the large
void spaces in porous concrete might have accelerated the drying
process and contributed further to the problem. Once placed, the
plastic sheets were held down at the edges by rocks, cinder blocks,
buckets, and pieces of wood. During the 24 hours after pouring,
the plastic sheets often came loose, causing the concrete to dry
too quickly.
Most of the problems that
occurred during construction were not anticipated. As the construction
team had built a satisfactory test pad, the only concern at the
start of the pour was the surface appearance. Unfortunately, due
to the project's relatively small construction window, there was
no extra time built into the construction schedule. The failure
of the first truckload of porous concrete caught the team by surprise.
As the team was unaware of the plant additives and unwashed aggregate,
the changes to the water mixture were made by trial and error,
causing mixed results. Besides the mix's design difficulties,
the inability to properly cover the material, and the short construction
window, failure of the surface clearly resulted from multiple
factors.
While the surface was not
satisfactory in appearance or durability, porosity was not a problem.
The surface drained quickly and easily, without significant ponding.
The porosity did not diminish during the year before replacement.
Reconstruction
Because of the surface
failure of the first installation, the porous concrete site was
redesigned and resurfaced in spring 2003. In addition to the lessons
learned from the initial construction, information gathered on
visits to other sites was included in the redesign and construction.
 |
| Figure
6. Centre County Visitor Center sidewalk; smooth, durable, and
porous, but evidencing multiple pours |
 |
| Figure
7. University of North Carolina parking lot |
 |
| Figure
8. One of the four test pads constructed to compare mixes and
methods |
Villanova University
representatives and the contractor visited three existing sites
before beginning the redesign. The first, to the Centre County Visitor
Center adjacent to Pennsylvania State University, was encouraging.
Porous concrete (no admixture) had been used to construct a sidewalk,
which had been rolled during construction. The surface was smooth
and durable, but the color variation of each pour was evident (Figure
6). The other two sites were near Raleigh, NC. The first was an
older site where the driveways and a cul-de-sac were all porous
concrete. Again the surface was durable. The second site was a very
large parking area at the University of North Carolina that had
included an admixture. The surface appeared durable, but the cosmetic
appearance was inconsistent (Figure 7). While this was acceptable
for a parking area, it was not acceptable for a central pedestrian
mall that was to be a showcase on Villanova's campus.
Based on the site visits,
it was decided to construct several concrete test pads to give the
contractor more experience and to check durability and surfacing
techniques. The first 200 ft2 pad (built in fall 2002) was acceptable
for durability, but the surface color varied excessively (partially
because the contractor tried several compaction techniques during
the pour). To provide a larger test, four 100 ft2 porous concrete
dumpster pads were installed at various locations on campus before
the start of reconstruction, as shown in Figure 8. These installations
were used to compare two mix designs and some compaction methods.
Several new quality control measures were imposed on the batch plant.
Two of the pads were constructed using a bonding agent, and two
were constructed without that admixture. A vibrating plate tamper
was used to compact two of the test pads, and a 48-inch, 50-gallon
plastic drum roller, filled with water, was used on the other two.
Following construction of the test pads, each was inspected and
core samples were taken for compaction strength testing. Each test
pad's porosity was verified by pouring water on the pad and observing
how quickly it infiltrated: It was determined that the mix containing
a binding agent and compacted with the roller provided the best
results. The roller was filled with water to exert a 10 psi load.
The mix containing bonding additive was more uniform in color and
produced higher-strength concrete. An important advantage of the
admixture was that the manufacturer provided experienced and effective
field supervision to train the contractor's crew.
 |
| Figure
9. Redesigned site |
 |
| Figure
10. The foreman is in charge of what, how much, and when. |
 |
| Figure
11. Rolling narrow strips of porous concrete around the perimeter |
Initial data and observations
of the site showed that the original design had more than enough
porous concrete surface, and this area could be decreased without
affecting the site's performance. Therefore, a new layout was designed
to include narrow strips of porous concrete around the perimeter
of each bed, with conventional concrete replacing the porous concrete
in the middle. Pavers remained along the perimeter. The impervious
concrete was crowned along the center strips to promote drainage
toward the porous strips on the perimeter. These narrow strips allowed
the concrete to be compacted using the 50 gal. roller instead of
the vibratory screed. The roller covered the entire width of the
surface and limited the distance the concrete had to be spread (Figures
9 and 11).
Several Villanovans had
complained that the original surface was too rough. The aggregate
used in the original mix was relatively sharp, crushed rock. A smoother
river pebble was used for the reconstruction. Review of the batch
plant's practices resulted in the new aggregate being fully washed
and dried before being introduced to the drum. The mix would be
delivered dry with no admixtures introduced.
The reconstruction began
on May 19, 2003, with the first day of pouring occurring two days
later. The spring weather was much more favorable than the hot
summer conditions during the initial construction. During the
reconstruction, the temperatures remained cool with highs in the
mid-70s. Many days were overcast with occasional drizzle. The
high humidity and cool temperatures were ideal for concrete hydration.
Applying the lessons learned
from the first pour, no water was added to the concrete mix until
it reached the site. This gave the workers total control over
what was added to the mix and the mixing times. Consistency of
the mix was ensured through pre-inspection of the concrete plant.
The bonding admixture's representative was in charge of onsite
concrete mixing and pouring.
From the moment the concrete
truck arrived, the foreman was in charge of what, how much, and
when to add the water and admixture. He carefully inspected the
concrete to ensure it had the consistency to properly consolidate.
When a problem arose, he decided the proper course of action. The
representative trained one of the contractor's foremen to recognize
and produce the proper mix consistency for later pours.
Each truckload contained
6-7 yd3 of material. Typically, 10 gallons of water per yard of
concrete were used, but this varied from 9 to 11 gallons, depending
on weather conditions. The foreman remained at the top of the truck
so he could see into the drum and examine the mix's consistency
(Figure 10). Batching typically lasted between 5 and 10 minutes.
After the water was added, the admixture was slowly introduced.
The specifications call for 3.3 gallons of admixture per yard of
concrete. After this was added, the concrete was thoroughly mixed
again for approximately 5 minutes before the drum was reversed for
release into the chute. The batches were often hand-sampled to visually
determine slump. It was at this point that the foreman would decide
if the consistency was correct or if it needed more water or mixing.
He would periodically feel the hydration rate (and resulting heat)
inside the drum by placing the palm of his hand on the rotating
drum's exterior. If it was satisfactory, the material was poured.
If it wasn't, steps were taken to remedy the situation until the
desired consistency was achieved. The entire process of mixing took
an average of 20 minutes from the introduction of water into the
drum to release for pouring. This relatively quick mixing process
might have played a key role in maintaining the concrete's workability
during the pour. Although the workability greatly improved, it also
became difficult at the end of each load as the concrete began to
hydrate. This is why the drum's maximum 9 yd3 capacity was not utilized.
Rakes were used to move
the concrete horizontally no more than 2 ft. Excessive movement
within the pour resulted in a blotchy surface. Troweling or movement
with shovels was not permitted because they left spots of glazed
surface. The rolling compaction technique proved superior to the
vibratory screed and plate tamper used in the initial construction.
The narrow pour widths allowed the crew to quickly prepare the
concrete for rolling and cover. It was found that wetting the
50-gallon roller prior to and during the compaction process helped
keep the concrete from sticking to its face. Immediately after
rolling, the concrete was covered with plastic sheets and these
were properly secured. This process was maintained throughout
the pour duration. The plastic was not removed until at least
48 hours later.
Current State
The reconstruction was
completed on May 30, 2003, and went much more smoothly than the
initial effort. No areas needed to be patched, removed, or repaired.
One truckload was rejected, however, because of poor consistency.
It was speculated that moisture left in the truck from a previous
job caused early hydration. Overall, the surface of the porous concrete
met expectations. The appearance of the site is greatly improved
as compared to the original design, and much of the surface remains
durable to date. The new river-pebble aggregate provides a smoother
and more aesthetically pleasing surface. The site has been observed
during multiple rainfall events and is porous.
 |
| Figure
12. Nonporous area |
 |
| Figure
13. Elevation differences can create a protruding edge that
is vulnerable to chipping |
The redesigned site lets
the central (impervious) concrete areas drain toward the porous
concrete border. In some locations, the runoff from the conventional
concrete is concentrated by the slopes and decorative grooves. This
concentrated flow sometimes exceeds the capacity of the porous concrete
strip's width during periods of intense rainfall.
Some minor inconsistencies
remain. In a few areas, the concrete appears almost glazed over
with excess cement (Figure 12). While these areas are probably
the most durable and strong, they have little or no porosity because
the voids have been clogged. This could be a result of the mix
being too wet. Observations made during the construction seem
to support this theory.
In some areas where the
porous concrete meets either conventional concrete or the decorative
pavers, there are slight differences in elevation (Figure 13).
This difference is likely a result of excess material deposited
prior to compaction. Before the concrete was compacted, the material
intentionally was elevated approximately 0.5 inches such that
the material, when sufficiently compacted, ideally would rest
at the same level as its border. With too much excess material,
the drum roller would compact the material but still leave the
material above its intended finished elevation. This protruding
edge could create a vulnerable spot where the concrete could be
chipped.
Material Testing
 |
| Figure
14. Test cylinder preparation: six firm blows with a 6-inch
tamp |
 |
| Figure
15. Reconstructed surfaceattractive and, so far, effective |
On May 29, 2003, four
sample cylinders were molded to conduct compressive strength tests.
Because there is no American Society for Testing and Materials standard
procedure for molding porous concrete cylinders, a method developed
by Eco-Creto of Texas Inc. was used. The method involved filling
a standard 6-inch diameter cylinder with concrete in three lifts.
Each lift was compacted using a 6-inch diameter tamp struck with
six firm blows (Figure 14). The cylinders then were covered and
allowed to cure. Two of the cylinders were broken on July 3, 2003.
The results of the two breaks were 3,460 and 3,412 psi. The samples
taken from that truck appeared to be too wet, however, and therefore
the concrete did not appear to have sufficient void space. This
might have accounted for the high compressive strengths. The remaining
two cylinders are being kept for future testing.
In conclusion, the reconstruction
of the porous surface was successful: porous, durable, smooth,
and attractive (Figure 15). Material problems have occurred on-site
over the winter. Although much of the pour remains in excellent
condition, areas of the porous concrete have deteriorated. This
is considered a material problem, and the contractor and material
supplier are working to correct it.
Design Recommendations
The following recommendations
are made.
Design the porous surface
as a series of narrow strips to promote surface uniformity.
Narrowing the width of the pour reduces movement during placement
of the material, allows for rolling the complete width with each
pass, facilitates immediate coverage to promote even hydration,
and minimizes visual ridges resulting from uneven rolling.
Use a series of perimeter
strips, and design the nonporous surface to drain as sheet flow
into the porous concrete surface. The infiltration capacity of porous concrete makes
it unnecessary for the whole area to be porous, but concentration
of runoff can overload the capacity of the porous concrete surface.
Runoff from the regular concrete follows the expansion joints
and can, during severe weather, concentrate and overload the porous
concrete. A better design to capture more runoff from intense
rainfall periods would anticipate the channeling effect of the
expansion joints and have the runoff cross multiple porous strips,
providing redundancy to protect against areas that clog over time.
This
type of BMP should be located in areas with a low risk of hazardous
spills. Villanova's site is
a pedestrian mall, located in the center of campus, with little
risk of catastrophic chemical spills or other catastrophes. The
only recourse for such spills would be total site reconstruction.
Generic concrete specifications
will not be adequate for inexperienced contractors to perform
a satisfactory porous concrete installation. Either the consulting engineer or the
contractor should enlist the assistance of industry manufacturers'
reps to specify batching and placement techniques and formulation.
Mistakes are irreversible and thus costly because this concrete
system has low initial slump and fast setup times.
The material specification
must be enforced. Mix proportions, additives, and composition are
critical. Do not assume your concrete plant operator understands
the importance of washed aggregates, additives, and so on. Water
should be added at the site. Carefully controlling the water volume
and the contact time is critical.
Owners should enter
into a general construction type of contract rather than attempt
to perform the work on a multiple-prime basis. Having single-point accountability makes the
general contractor responsible for all tolerances, coordination
of excavation and bed preparation, and concrete mixing/placement
activities.
Construction Recommendations
Consultants and contractors
must recognize that batching and placement practices for porous
concrete vary greatly compared to those for conventional (impervious)
structural concrete.
Regarding batching,
concrete should be in 5-7 yd3 batches, not the 9 yd3
capability of most drums. Delivery of dry mix is necessary, and it must be batched in
dry (not washed-out) drums. If a binder admixture is specified,
no other conventional concrete admixture should be introduced
without assent of the bonding agent's manufacturer. Aggregates
must be fully washed and dried before being batched because excessive
fines diminish the function of porous concrete and affect field
introduction of water and the bonding agent, which should be performed
only by experienced porous concrete personnel. Due to the product's
very low slump, its workability must be determined visually before
the mix is run down the chute.
Adjustments in the water
quantity, the number of drum rotations, and admixture introduction
must be performed quickly to ensure workability. Hydration heat monitoring in the drum is
important.
Regarding placement
practices, for multiple test pours, using the same foreman and
crew as will be used for actual construction is strongly recommended.
Test pads should be at least 200 ft2 to detect surface
unevenness. A properly batched mix cannot be moved horizontally
more than a couple of feet from the point of placement. This is
a major contrast to conventional concrete exhibiting typical 3-
to 5-inch slumps. Use rakes instead of flat devices, such as shovels,
screed boards, and trowels, which should not be used to shift
or level concrete. Using such devices will produce splotchy surfaces.
Installers must plan and execute placement to effect the items
above. In conventional concrete practice, concrete leaves the
chute and forms puddles, which first are worked by laborers several
feet horizontally, next are screeded, and then are troweled smooth
by cement finishers. Concrete's lack of slump and fast setup characteristics
require steady movement of porous concrete chutes to replace manual
working so placement is not in pools but rather in continuous
bands that need minimal working before rolling. Such placement
requires laborers to develop a cement finisher's eye for level
and an understanding of the drum's discharge rate down the chute.
Critical is the degree of communication between the laborers and
the person (foreman) responsible for field mixing at the truck's
drum. Rolling is the preferred compaction method. Vibratory tampers
create ridges that visually are difficult to detect until after
the concrete has hydrated. Careful hand tamping might be necessary
in areas where rollers cannot reach. Rollers also will leave small
ridges that are difficult to detect in unhydrated concrete.
Concrete must be tightly
covered for a minimum of 48 hours after placement.
Existing concrete material
specifications and testing standards are inadequate both for batch
plants not experienced with porous concrete and when proprietary
binding admixtures are used. The only people capable of ensuring
proper batching and placement are the bonding admixture manufacturers
or contractors with proven porous concrete installation track
records.
Flexibility must be
included in the construction schedule. Porous concrete is less
forgiving than regular concrete. You cannot take shortcuts,
and pouring in extreme weather conditions is not an option. Some
loads might have to be discarded. Extra time must be built into
the construction schedule to accommodate material and environmental
contingencies.
Smaller pour volumes
are better. The material should be rolled and covered immediately.
The fast setup requires timely placement, rolling, and covering.
At the end of the pours, the material is more difficult to move,
and the appearance is not as good.
Villanova Urban Stormwater
Partnership
The
mission of VUSP is to advance the evolving comprehensive stormwater
management field and foster the development of public and private
partnerships through research on innovative stormwater BMPs, directed
studies, technology transfer, and education. Firms interested in
joining the partnership can access the VUSP Web site www.villanova.edu/VUSP.
Acknowledgments
Funding for the project
was through the Pennsylvania Section 319 Nonpoint Source Pollution
Program. This support does not imply endorsement of this project
by US EPA or the Pennsylvania Department of Environmental Protection.
The design and construction
were overseen by Robert Morro, executive director of facilities;
James Zaleski, director of engineering and systems; and Leo Kob
of Villanova's Facility Management Office.
The design firm for the
infiltration portions of the project was Cahill Associates of
West Chester, PA. The site contractor was N. Abbonizio Contractors.
Eco-Creto of Texas Inc. was the admixture supplier.
Reference
Traver, Robert. 2000.
"Development of a BMP Research and Demonstration Park," 9th
International Conference on Urban Storm Drainage. Environmental
and Water Research Institute, American Society of Civil Engineers.
Robert
Traver and Andrea Welker are professors in the Department of Civil
and Environmental Engineering at Villlanova University and direct
the Villanova Urban Stormwater Partnership (VUSP). Clay Emerson
is the VUSP research associate. Michael Kwiatkowski and Tyler Ladd
are graduate assistants. Leo Kob is with the Villanova University
Facility Management Office.
SW
July/August 2004
|